Proper operation and regular maintenance of a ram blowout preventer are not optional — they are the difference between a functioning well control barrier and a failure that can lead to a blowout. This guide compiles essential operating procedures for CAMTOP WU-series ram BOPs, consistent with API RP 53.
⚠️ Safety First: BOP operations must only be performed by trained and certified well control personnel.
1. Pre-Installation Inspection
- Verify the BOP model, bore size, and pressure rating match the well design
- Check the top and bottom flange faces for nicks, corrosion, or ring groove damage
- Inspect ram assemblies — verify correct ram type is installed
- Check all bonnet bolts for proper torque per CAMTOP torque specification table
- Verify manual lock screws are fully retracted
- Review factory acceptance test (FAT) documentation
2. Hydraulic Closing Procedure
Required hydraulic pressure: 1,200–1,500 PSI from the BOP control unit.
- Confirm BOP control unit is pressurized to 1,200–1,500 PSI
- Confirm drill pipe position in the bore
- Actuate the closing valve on the BOP control panel
- Observe ram closure indicator and confirm closing pressure
- Verify closure by pressure testing the BOP
- Record closing time — must be ≤30 seconds per API RP 53
3. Manual Lock Procedure
- Confirm rams are fully closed at operating hydraulic pressure
- Turn manual lock hand wheel clockwise until it stops, then tighten to specified torque
- Record in rig log that manual locks are engaged
⚠️ Before Opening: Always back out manual lock screws fully before applying hydraulic opening pressure.
4. Function Testing Requirements (API RP 53)
| Test Type | Frequency | Acceptance Criteria |
|---|---|---|
| Pre-spud function test | Before each well | Full closure in ≤30 sec; no leakage |
| Low-pressure seal test | Pre-spud + every 7 days | 200–300 PSI; zero pressure drop over 5 min |
| High-pressure seal test | Pre-spud + as required | Rated working pressure; zero pressure drop |
5. Ram Packing Replacement
Replace when: after any emergency closure, when pressure test shows ≥10 PSI/min leak-down, or after each well program.
- Verify well is dead and BOP is fully depressurized
- Bleed all hydraulic lines
- Unbolt bonnet bolts per CAMTOP torque sequence
- Swing bonnet open to expose ram assembly
- Remove and disassemble ram assembly; clean all surfaces
- Install new CAMTOP OEM packing elements per kit assembly drawing
- Reassemble and conduct pressure function test before returning to service